In short. A homebuyer may file before the state RERA authority or the consumer commission, but should not pursue the same relief in both. Newtech Promoters (2021) and Imperia Structures v Anil Patni (2020) hold that RERA does not bar consumer complaints. Choose RERA for a quick refund or delay interest at the prescribed rate; choose the consumer commission for broader compensation or projects outside RERA.
This post compares the two forums for one kind of buyer: someone who booked a flat, plot or villa from a builder in Delhi NCR and now has a grievance about delay, refund, defects, extra charges or a one-sided agreement. It sets out what each forum can give you, what it costs, how long it tends to take, who the builder will argue is not entitled, and how each forum's order is enforced. The detailed filing steps for RERA are in filing a RERA complaint in Delhi, UP and Haryana, and for the consumer side in filing a consumer complaint online on e-Jagriti.
The choice matters more than most buyers think, because switching forums midway costs time and sometimes money. For an overview of how consumer cases run, see our page on consumer and competition laws; for builder disputes generally, see real estate and infrastructure laws.
- RERA law
- Real Estate (Regulation and Development) Act 2016, section 31
- Consumer law
- Consumer Protection Act 2019
- Both available?
- Yes: Imperia Structures (2020), Newtech Promoters (2021)
- Same relief in both?
- No, choose one forum for each relief
- Consumer time limit
- 2 years from cause of action, section 69
- Switching to RERA
- Section 71(1) proviso allows withdrawal from consumer forum
Can a flat buyer go to both RERA and the consumer court?
A buyer can choose either forum, but should not run both for the same relief at the same time. Section 79 of RERA bars civil courts from entertaining matters the RERA authority can decide, but it does not mention consumer commissions, and section 88 says RERA applies in addition to, not in derogation of, other laws. In Imperia Structures Ltd v Anil Patni (2020) the Supreme Court held that a consumer complaint by an allottee against a builder remains maintainable even for a project registered under RERA.
The Supreme Court repeated this in Newtech Promoters and Developers v State of UP (2021). It described the remedies as concurrent and said it is for the allottee to choose: proceed under the Consumer Protection Act, or file before the RERA authority or adjudicating officer. What the law does not allow is two parallel cases asking for the same refund or the same interest. A builder facing both will ask one forum to stay its hand or dismiss the second case, and it will usually succeed.
Different reliefs are a different matter. A buyer can, for example, have a delay interest complaint before RERA and a separate consumer complaint about defects found after possession, because the causes and the reliefs are not the same. The test is whether the second case is really the first one in a new place.
RERA authority vs consumer commission: side by side
The general position in Delhi, Uttar Pradesh and Haryana. Details depend on the state rules and the commission's own regulations.
| Point | RERA authority | Consumer commission |
|---|---|---|
| Who can file | Any allottee, including investors; association of allottees | A "consumer"; buyers for commercial purposes can be excluded |
| Which projects | Projects registered or required to be registered under RERA | Any project, including pre-RERA, exempt and completed ones |
| Where to file | Authority of the state where the project is | Where the builder works, where the cause arose, or where you live or work |
| Fee | Fixed, ₹1,000 in UP and Haryana | Nil up to ₹5 lakh; modest slab fee above that |
| Which level | One authority regardless of amount | District up to ₹50 lakh paid; State up to ₹2 crore; NCDRC above ₹2 crore |
| Interest | Prescribed rate linked to SBI MCLR, from each payment | At the commission's discretion, often with separate compensation |
| Compensation | Separate complaint before the adjudicating officer | In the same complaint, along with costs |
| Builder's appeal | Tribunal within 60 days; builder must deposit the full amount ordered | Appeal with deposit of 50% of the amount ordered |
| Enforcement | Recovery certificate or execution; penalty under section 63 | Execution as a decree; imprisonment or fine under section 72 |
When is RERA the better choice?
RERA is usually the better choice when what you want is the statutory relief: a refund with interest under section 18, or interest for every month of delay until possession. The authority applies the rate in the state rules mechanically, from the date of each payment, and it does not have to be persuaded that the interest is fair. For a large flat, the fixed fee is also far cheaper than slab fees at the State Commission or NCDRC.
RERA is also the better forum when the builder is likely to argue that you are an investor. Consumer law excludes persons who buy for a commercial purpose, and builders routinely argue that a buyer with two flats, a buyer who has rented out another property, or a buyer of a shop is not a consumer. RERA protects every allottee, whatever the purpose of the purchase. Assured return and lease-back deals in commercial projects are the most common example.
The appeal deposit favours buyers before RERA. Under section 43(5), a promoter must deposit at least 30 per cent of any penalty, or the total amount ordered to be paid to the allottee with interest and compensation, before the Appellate Tribunal will hear its appeal. That deposit often becomes the buyer's money in hand at the end of the appeal. Consumer appeals require a 50 per cent deposit, which is still useful but leaves half the order unsecured.
When is the consumer commission the better choice?
The consumer commission is often better when your loss goes beyond interest: years of rent, a job relocation that came to nothing, medical cost, a defective flat needing repairs, or harassment through wrong demands. A consumer commission can award compensation and costs in the same complaint, while under RERA compensation needs a separate case before the adjudicating officer. Commissions also have express power to declare unfair contract terms null, the State Commission under section 49(2) and the National Commission under section 59(2).
It is the only option where RERA does not apply: a project that received its completion certificate before RERA came into force, a small project exempt from registration, or a dispute with a development authority's own housing scheme that is not a registered project. Defect complaints years after possession, once the five-year structural defect liability under section 14(3) of RERA has run, also usually belong in the consumer commission.
Place of filing can decide the matter for some buyers. Under section 34(2)(d) of the Consumer Protection Act 2019, a District Commission complaint can be filed where the complainant resides or personally works for gain. A buyer living in Dwarka who bought in Gurugram can file before the District Commission in Delhi instead of travelling to Gurugram, and the same rule applies at the State Commission level. RERA complaints, by contrast, always go to the state where the project is.
The provisions that decide which forum you can use
Five provisions settle most arguments about forum.
Section 79, RERA
Bars civil courts from entertaining suits on matters the authority, adjudicating officer or Tribunal can decide. Consumer commissions are not civil courts for this purpose, which is why they continue to hear builder cases.
Section 88, RERA
RERA is in addition to, and not in derogation of, any other law in force. This keeps the Consumer Protection Act available to homebuyers.
Section 71(1) proviso, RERA
A person whose complaint about matters under sections 12, 14, 18 and 19 is pending before a consumer forum may, with the forum's permission, withdraw it and file an application before the adjudicating officer.
Section 2(7), Consumer Protection Act 2019
Defines a consumer and excludes a person who obtains goods or services for resale or for any commercial purpose. Builders rely on this to argue that investors are outside consumer law.
Section 69, Consumer Protection Act 2019
A complaint must be filed within two years of the cause of action, with delay condonable for sufficient cause. Non-delivery of a flat is generally treated as a continuing cause, but refusal of a refund or cancellation of the unit can start the clock.
Which is faster, RERA or consumer court?
There is no fixed answer, because both forums in Delhi NCR carry heavy loads and the timing depends on the bench and how hard the builder fights. As a general pattern, a straightforward refund or delay interest complaint before RERA is often decided faster than the same claim before a State Commission or the NCDRC, because the authority has a narrower question to answer and applies a fixed formula. A District Commission complaint for a smaller amount can also move reasonably quickly.
Speed to the order is only part of it. Ask how quickly you can actually be paid. A RERA order that the builder neither pays nor appeals goes to recovery through the district collector, which in Noida and Greater Noida has a long queue. A consumer order that is ignored can be enforced as a decree, and section 72 of the Consumer Protection Act makes non-compliance punishable with imprisonment from one month to three years, a fine from ₹25,000 to ₹1 lakh, or both. Builders' directors tend to respond to a warrant faster than to a recovery certificate.
Does the consumer court award more than RERA?
Sometimes. RERA gives a predictable rate tied to SBI's MCLR, plus whatever the adjudicating officer later awards as compensation. A consumer commission fixes interest and compensation in its own discretion, and in delay cases commissions have often awarded simple interest at rates in the range of 6 to 9 per cent with separate compensation and costs. Whether that adds up to more than the RERA figure depends on the dates, the amount and the commission.
Do not choose a forum by the highest number you have heard. The Supreme Court has discouraged overlapping awards that pay the buyer twice for the same delay, and appellate forums trim compensation that is not tied to proven loss. A modest, well-founded claim that survives appeal is worth more than a large award that is cut down or takes years to collect.
Are you a consumer if you bought the flat as an investment?
Possibly not, and this is the single biggest risk on the consumer side. A buyer who purchases a flat to live in, or for a close family member to live in, is a consumer. A buyer who books several units in the same project, buys shops or office space to lease, or deals in property as a business, may be held to have bought for a commercial purpose and thrown out of the consumer commission.
The builder generally has to prove commercial purpose; owning a second property is not enough by itself. But if your file shows a lease-back arrangement, an assured return clause, or a booking made through a broker for resale, assume the argument will be made. When Advocate B.K. Singh is asked which forum to use, the purpose of the purchase is one of the first questions he asks, because for an investor the answer is almost always RERA.
A made-up example: two buyers in the same Noida tower
Here's a made-up example. Two buyers booked flats in the same delayed Noida tower in 2018. Meera paid ₹48 lakh for a flat she meant to live in; she rents in Lajpat Nagar, works in Connaught Place, and has rent receipts for six years. Sanjay paid ₹1.4 crore for two flats and a ground-floor shop under a scheme that promised him monthly assured returns until possession.
Meera's loss goes well beyond interest: six years of rent and a claim that the builder's revised demand for parking is unfair. Her payments fall within the District Commission's limit, she can file in Delhi where she lives, and the commission can deal with interest, compensation and the unfair demand in one complaint. She files in the consumer commission.
Sanjay would face a strong commercial-purpose objection in the consumer commission. Before RERA, his status as an allottee is not in doubt, the delay interest runs at the prescribed rate on the whole amount, and the assured return dispute can be raised before the authority. He files before UP RERA, and keeps his compensation claim for the adjudicating officer.
How to choose between RERA and the consumer commission
Confirm RERA applies
Check whether the project is registered on the state portal or should have been. If it was completed before RERA or is exempt, the consumer commission or civil court is your forum.
Define what you want
Write down the relief in one line: refund with interest, delay interest until possession, compensation for loss, rectification of defects, or striking down a demand. Statutory refund and interest point to RERA; broad compensation points to the consumer side.
Test the consumer question
Ask honestly whether the builder can argue commercial purpose. If yes, RERA removes the risk.
Work out place and level
For the consumer route, find the commission by amount paid and decide whether filing where you live helps. For RERA, the project's state decides it.
Look at the builder's finances
Check pending recovery certificates, insolvency petitions and other stalled projects. A financially weak builder makes enforcement, and the appeal deposit, more important than the size of the award.
Choose once and plead fully
Put every related relief into the chosen forum, or file separate cases only where the reliefs are genuinely different. Do not open a second case for the same claim.
Already filed in the consumer court and want to move to RERA?
You can, but think before you do it. The proviso to section 71(1) of RERA lets a person with a pending consumer complaint about matters under sections 12, 14, 18 and 19 withdraw it with the consumer forum's permission and file before the adjudicating officer. In practice buyers who want refund or delay interest withdraw with liberty and file before the RERA authority, which after Newtech is the right forum for those reliefs.
Moving makes sense if the consumer case has barely started, the builder is raising a strong commercial-purpose objection, or the commission's list means years before final hearing. It rarely makes sense if pleadings are complete and arguments are close; you lose the time already spent and the builder gets a fresh round of replies. Moving the other way, from RERA to a consumer commission, is less common and should only be done with a formal withdrawal so that the builder cannot argue the first case is still alive.
Defects after possession: RERA or consumer court?
For defects noticed within five years of possession, RERA gives a specific remedy. Section 14(3) makes the promoter responsible for rectifying any structural defect, or any other defect in workmanship, quality or services, brought to its notice within five years of handing over possession. The promoter must fix it within 30 days at no charge, and if it does not, the allottee is entitled to compensation. Seepage, cracks, failed waterproofing, poor plumbing and lifts that keep breaking down all come up under this provision.
The consumer commission can deal with the same defects as deficiency in service, and it is the natural forum after the five years have passed or where the defect claim is tied up with a larger claim for compensation. Whichever you choose, start by writing to the builder listing each defect with photographs and dates, because the 30 days under section 14(3) run from the builder being told. An engineer's or architect's inspection report, prepared before any repair, is the evidence both forums look for.
A group of buyers: association complaint or class complaint?
When many buyers in one project have the same grievance, both forums allow a collective case. Under RERA, a registered association of allottees can file under section 31, which works well for common issues such as the occupancy certificate, the conveyance deed, the handover of common areas or a society-wide demand for extra charges. Under the Consumer Protection Act, section 35(1)(c) allows one or more consumers with the same interest to file on behalf of, or for the benefit of, all the consumers so interested, with the commission's permission.
Collective cases save cost and carry weight, but money claims are usually better filed individually, because each buyer's payments, dates and loan arrangements differ. A practical pattern in Delhi NCR is an association case for the common reliefs, with individual refund or delay interest complaints filed alongside and heard together. Agree in writing within the group who instructs the lawyer, who pays what and what happens if some members settle.
What about the civil court or a criminal complaint?
For matters RERA can decide, section 79 keeps the civil court out, so a suit for refund against a builder of a registered project usually fails at the threshold. Civil suits remain the route for disputes RERA and consumer law do not cover, such as title disputes, or a commercial lease of an entire building between two companies. The question of whether a builder can be made to execute a sale deed in a non-RERA transaction is covered in our post on specific performance of an agreement to sell.
Criminal complaints for cheating under section 318 of the Bharatiya Nyaya Sanhita, often through the Economic Offences Wing in Delhi or the police in Gautam Buddh Nagar, are filed in cases of double allotment, diversion of buyers' money or fake approvals. They can put real pressure on a builder, but they do not give you a refund order and courts are quick to quash complaints that dress up a contractual delay as a crime. Use them where the facts show deception from the start, not as a substitute for RERA or the consumer commission.
Documents that help you choose a forum
These are the papers to look at before deciding. Most of them will become annexures to whichever complaint you file.
To test whether RERA applies
- Project's RERA registration page, or proof that none exists
- Completion or occupancy certificate date, if any
- Number of units and land area of the project
To test the consumer question
- Booking form showing the purpose of purchase
- Any assured return, lease-back or buy-back agreement
- Details of other properties you own
- Proof you live in rented accommodation
To size the claim
- Payment receipts and bank statements
- Rent receipts and lease deeds
- Loan statements and interest certificates
- Builder's demands you dispute
Mistakes buyers make when picking a forum
- Filing in both for the same refund. The builder will use it to delay both cases, and one will be dismissed.
- Investors going to the consumer commission. A commercial-purpose objection can end the case after years of hearings.
- Choosing by the size of awards heard about. What counts is what survives appeal and can be recovered.
- Ignoring the consumer limitation period. Once the builder cancels the unit or refuses a refund in writing, the two years in section 69 may start running. Our post on the two-year limit for consumer complaints explains how delay is condoned.
- Filing in the wrong consumer commission. Pecuniary jurisdiction depends on the amount paid, not the amount claimed. See which consumer commission: pecuniary limits explained.
- Forgetting enforcement. The forum that gives the larger order is not always the one that gets you paid sooner.
What happens if the builder does not pay after either order?
Both forums have teeth, of different kinds. A RERA order is recovered as arrears of land revenue through a recovery certificate to the district collector, or executed under the state rules, and the authority can add penalties under section 63 for non-compliance. These steps are explained in recovery certificates and execution of RERA orders.
A consumer order is executed as a decree under section 71 of the Consumer Protection Act, with attachment of the builder's accounts and property, and section 72 adds the threat of imprisonment and fine for wilful non-compliance. That process is covered in our post on enforcing a consumer commission order. If the builder goes into insolvency, both routes pause during the moratorium and you claim in the insolvency instead.
Deciding this week: a short checklist
- Look up the project on the state RERA portal and note whether it is registered.
- Write the one relief you want most in a single sentence.
- Note anything in your file that could suggest a commercial purpose.
- Total the amount you have paid to see which consumer commission would hear it.
- Check whether filing near your home under the consumer law would help you attend hearings.
- Search for other complaints, recovery certificates or insolvency petitions against the builder.
- If a consumer case is already pending, decide whether to continue or withdraw before filing anything new.
Getting a second view before you commit
The forum decision is cheap to get right at the start and expensive to fix later. If you want an advocate to look at your agreement, payments and the builder's position and suggest which forum suits your case, the team of Advocate B.K. Singh at B.K. Singh & Associates can read the papers and explain the options. You can reach them through our online legal enquiry, or read about consumer cases before the Delhi commissions and the NCDRC on our consumer court practice page.
Frequently asked questions
Is RERA better than consumer court for flat delay?
For a straightforward refund or delay interest claim, RERA is usually quicker, cheaper and applies a fixed rate, and it protects investors as well as end users. The consumer commission can be better where you want wider compensation in one case, or where RERA does not apply to the project.
Can I file a case in both RERA and NCDRC?
Not for the same relief. The Supreme Court has held the remedies are concurrent and the buyer must choose. You can pursue genuinely different reliefs in different forums, such as delay interest before RERA and a later defect claim in the consumer commission.
Can I withdraw my consumer complaint and file in RERA?
Yes. The proviso to section 71(1) of RERA allows a pending consumer complaint on matters under sections 12, 14, 18 and 19 to be withdrawn with the forum's permission and filed under RERA. Ask for withdrawal with liberty to file afresh, so there is no argument later.
Is an investor flat buyer a consumer?
Not always. The Consumer Protection Act excludes purchases for a commercial purpose, and builders argue that buyers of multiple units, shops or assured-return units are investors. RERA has no such exclusion, so investors usually do better there.
Which consumer commission hears a builder case of ₹1 crore?
Pecuniary jurisdiction depends on the amount paid for the flat. If you paid more than ₹50 lakh and up to ₹2 crore, the State Commission hears it; above ₹2 crore, the NCDRC. Up to ₹50 lakh, the District Commission.
Can I file a consumer complaint where I live instead of where the flat is?
Yes. Section 34(2)(d) of the Consumer Protection Act 2019 allows a complaint where the complainant resides or personally works for gain. RERA complaints, by contrast, must be filed in the state where the project is located.
Does the civil court have jurisdiction over a RERA project dispute?
Generally no. Section 79 of RERA bars civil courts from matters the RERA authority, adjudicating officer or Tribunal can decide. Civil suits remain for issues outside RERA, such as title disputes.
What if my project was completed before RERA came into force?
If the project had its completion certificate before RERA applied, a RERA complaint is generally not maintainable. Your remedy is the consumer commission, or a civil suit for matters outside consumer law.
Which forum is cheaper for a large flat?
RERA charges a fixed fee, ₹1,000 in UP and Haryana, whatever the amount. Consumer commissions charge nothing up to ₹5 lakh but slab fees above that, which are still modest but higher for large claims.
Can the consumer commission strike down a builder agreement clause?
Yes. The State Commission and the National Commission have express power to declare unfair contract terms null and void, under sections 49(2) and 59(2) of the Consumer Protection Act 2019. RERA authorities also disregard one-sided interest and penalty clauses.
Is filing a police complaint against the builder better than RERA?
Rarely, unless there was deception from the start, such as double allotment or fake approvals. A criminal case does not give you a refund order, and courts often quash complaints that turn a contractual delay into cheating.
How long does a builder have to appeal in each forum?
A RERA order can be appealed to the Appellate Tribunal within 60 days, with the builder depositing the amount ordered. A District Commission order can be appealed within 45 days with a 50 per cent deposit, and a State Commission order within 30 days, also with a 50 per cent deposit.